Daily Archives: 1 May 2012


Vineyard Hill is in Water!!

Eight months from site acquisition volunteers complete re-construction of 300 metre stretch of canal The seven months of preparations made by the volunteers at Vineyard Hill led to a successful Waterway Recovery Group Camp that took place over the first two weeks of April. Meetings with stakeholders to explain and agree our proposals, preparing drawings and procedures, procuring materials, setting out the line and the levels on the ground, preparing […]